Skip to main content
Redevelopment
Back

Hung Fook Street / Kai Ming Street Development Project (KC-011)

Location
Nos. 16-46 Hung Fook Street (even nos. only), Nos. 21-39 Kai Ming Street (odd nos. only),and 35-37 Wing Kwong Street (odd nos. only), To Kwa Wan, Kowloon City
Area
About 2,635sq.m.
Affected buildings
28 street numbers of buildings
Affected population
About 821
Affected property interests
About 230
Affected households
About 319
Hung Fook Street / Kai Ming Street Development Project
Hung Fook Street / Kai Ming Street Development Project

Project Development Information


Total GFA About 21,960 sq.m.
Commercial GFA About 3,660 sq.m.
Residential GFA About 18,300 sq.m.

Project Status


Project commencement was gazetted on 3 June 2016.

The Secretary for Development (SDEV) has considered the project and the related information and authorized the URA to proceed with the project without any amendment on 22 February 2017.  The SDEV's decision was published in the Gazette on 3 March 2017.

Land of the project has been reverted to the Government. 

Demolition work of existing buildings were completed. This project was combined with DL-8:KC for re-development.

Project Programme


Targeted completion by 2026/2027.

More Information


The project is implemented in accordance with the "Urban Renewal Strategy" ("URS") (2011) which includes the flat-for-flat options as an alternative option to cash compensation to domestic owner-occupiers. They can consider cash compensation or using it to buy a new flat-for-flat in-situ in the new development or in the same district or in Kai Tak development.

 

     

Back