Kai Ming Street / Wing Kwong Street Development Project (KC-013)
- Location
- Nos. 4-24 Kai Ming Street (even nos.) and Nos. 26-28 Kai Ming Street (even nos.) and Nos. 29-33 Wing Kwong Street (odd nos.), To Kwa Wan, Kowloon City
- Area
- About 1,749 sq.m
- Affected buildings
- 16 street numbers of buildings
- Affected population
- About 463
- Affected property interests
- About 125
- Affected households
- About 204
Project Development Information
Total GFA | About 11,797 sq.m. |
Commercial GFA | About 1,966 sq.m. |
Residential GFA | About 9,831 sq.m. |
Project Status
Project commencement was gazetted on 17 March 2017.
The Secretary for Development (SDEV) has considered the project and the related information and authorized the URA to proceed with the project without any amendment on 9 October 2017. The SDEV’s decision was first published in the Gazette on 13 October 2017.
Land of the project has been reverted to the Government.
Demolition work of existing buildings were completed. This project was combined with KC:012 for re-development.
Construction works in progress.
Project Programme
Targeted completion by 2026/27.
More Information
The project is implemented in accordance with the "Urban Renewal Strategy" ("URS") (2011) which includes the flat-for-flat options as an alternative option to cash compensation to domestic owner-occupiers. They can consider cash compensation or using it to buy a new flat-for-flat in-situ in the new development or in the same district or in Kai Tak development.