Skip to main content



Tung Chau Street / Kweilin Street Demand-Led Redevelopment Project (DL-5:SSP)

270-286 Tung Chau Street / 1-5 Kweilin Street, Sham Shui Po, Kowloon
About 1,490 square metres
Affected buildings
1 block
Affected population
About 552
Affected property interests
About 171
Affected households
About 248
Site Photo
Site Photo

Project Development Information

Total GFA About 13,410 square metres
Residential Flats About 209
Commercial GFA About 4,320 square metres

Project Status

The project was commenced on 12 April 2013. 

No objection to the project was received by the URA during the two-month publication period (12 April to 13 June 2013).

SDEV has considered the project and authorized the URA to proceed with the project on 26 September 2013.

S.16 application to allow commercial uses on 3/F and 4/F was approved by Town Planning Board in March 2017.

Project Programme

Targeted completion by 2023/2024.

More Information

The projected is implemented is accordance with the Urban Renewal Strategy (2011) which includes the flat-for-flat options to be offered as an alternative options to cash compensate to domestic owner-occupiers.  They can consider cash compensation or using it to buy a new flat-for-flat in-situ in the new development or in the same district or in Kai Tak Development.